Ready-to-use Excel files for 23 demolition, breaking-out and dismantling items for renovation projects (12 from the BOQ + 11 added items), each with the same six sections.
Why these files matter
- A separate item for each kind of work: lump-sum dismantling, masonry demolition, breaking out plaster, cladding and floors, removing ceilings, stair treads and kerbs, and stripping roof insulation.
- Extra work you will meet on site: RC demolition, diamond-saw cutting, core drilling, temporary shoring and debris removal, each flagged as needing a variation order.
- Measured before it disappears: a joint survey record signed by both parties, because demolished work can’t be measured again.
- Protecting what stays: light breakers only, load limits on the roof, and any damage repaired at the contractor’s cost.
- Salvage belongs to the owner: handed over with formal records before the item is paid.
Who these files are for: renovation contractors, supervision engineers, and cost and contracts engineers.